WSP | Parsons Brinckerhoff was appointed to facilitate compliance with the National Railway Safety Regulator Act for Grootegeluk Coal Mine.

Challenges

Our client needed to ensure quarterly track inspections were conducted on the Grootegeluk siding to ensure necessary safety on the railway network.

Our Approach / Services

Scope of works included quarterly inspections of the on-site railway, annual application process to obtain the required permit, level crossing assessments and stacker reclaimer inspections and reporting.

  • Routine track inspection
  • Track condition assessments and reports
  • Stacker reclaimer conditions assessment and reports
  • Maintenance planning and scheduling
  • Budget control
  • Materials procurement
  • Engineers representative
  • Railway permit applications and quarterly reporting to the RSR
  • Incident investigations
  • Level crossing assessments
  • Contract administration and management

Facts and Figures

Client: Exxaro Coal

Project Date: February 2016 – Current (3-year contact)

Project Fee: ZAR 500,000